(According to CI/Sfb)
| Table 0 – Physical Environment | ||
| 9 | Common Facilities | Meas. Unit |
| 91 | Circulation | – |
| 92 | Resting and work | – |
| 93 | Culinary | vg / u |
| 94 | Sanitary and hygiene | – |
| Table 1 – Elements | ||
| 1 | Substructure | |
| 2 | Primary Elements | Meas. Unit |
| 21 | External Walls | m2 |
| 22 | Internal Walls | m2 |
| 23 | Floors | m2 |
| 23.01 – 23.49 | External | m2 |
| 23.50 – 23.99 | Internal | m2 |
| 24 | Stairs, Rampas | – |
| 25 | Façade Shading Systems | m2 / u |
| 26 | Balconys’ stalls and Drying Areas | u |
| 27 | Roofs | m2 |
| 28 | Shafts | – |
| 29 | Parts of Elements (Pre-Fabricated) | u |
| 3 | Secondary Elements | Meas. Unit |
| 31 | External Doors and Windows | u |
| 31F | Fire Rated | u |
| 31W | Wood | u |
| 31M | Metallic | u |
| 31G | Glass | u |
| 31T | Curtain Wall | u |
| 32 | Internal Doors and Windows | u |
| 32F | Fire Rated | u |
| 32W | Wood | u |
| 32M | Metalic | u |
| 32G | Glass | u |
| 32T | Curtain Wall | u |
| 33 | Skirtings | m |
| 33.01 – 33.49 | External | m |
| 33.50 – 33.99 | Internal | m |
| 34 | Stairs Railings | m |
| 34.01 – 34.49 | External | m |
| 34.50 – 34.99 | Internal | m |
| 35 | Suspended Ceilings | m2 |
| 35.01 – 35.49 | External | m2 |
| 35.50 – 35.99 | Internal | m2 |
| 36 | Ceiling Moldings & Coves | m |
| 36.01 – 36.49 | External | m |
| 36.50 – 36.99 | Internal | m |
| 37 | Chimneys and Roofs’ Technical Areas | u |
| 38 | Railings | m |
| 39 | Coping, Sills and Thresholds | m |
| 39.01 – 39.49 | External | m |
| 39.50 – 39.99 | Internal | m |
| 4 | Finishes | Meas. Unit |
| 41 | External Wall | m2 |
| 42 | Internal Wall | m2 |
| 43 | Floor | m2 |
| 43.01 – 43.49 | External | m2 |
| 43.50 – 43.99 | Internal | m2 |
| 44 | Stair | m2 |
| 44.01 – 44.49 | External | m2 |
| 44.50 – 44.99 | Internal | m2 |
| 45 | Ceiling | m2 |
| 45.01 – 45.49 | External | m2 |
| 45.50 – 45.99 | Internal | m2 |
| 46 | Equipment | m2 |
| 47 | Roof | m2 |
| 48 | Other Finishes to Structure | m2 |
| 49 | Parts of Elements | m2 |
| 5 | Piped and Ducted | |
| 6 | Electrical and Mechanical | Meas. Unit |
| 63 | Lighting | m / u |
| 67 | Lifts | u |
| 7 | Fixed Equipments | Meas. Unit |
| 72 | Resting and work (Furniture) | u |
| 73 | Culinary (Kitchen) | u |
| 74 | Sanitary and hygiene (Bathroom) | u |
| 76 | Storage (Fixed Equipents / Closet) | u |
| 78 | Others | u |
| 8 | Loose Furniture and Equipment (Interior Design) | Meas. Unit |
| 82 | Resting and work (Furniture) | u |
| 83 | Culinary (Kitchen) | u |
| 84 | Sanitary and hygiene (Bathroom Accessories) | u |
| 86 | Storage (Lockers) | u |
| 88 | Others | u |
| Table 3 Materiais | ||
| Special Purposes | Meas. Unit | |
| m | Inorganic Fibers (Insulations, …) | m2 |
| r | Plaster, Mortars | m2 |
| r.01 – r.49 | External | m2 |
| r.50 – r.99 | Internal | m2 |
| v | Paints | m2 |
| v.01 – v.49 | External | m2 |
| v.50 – v.99 | Internal | m2 |
| y | Composite (Vynil,..) | m2 |
| Table 4 – Activities | ||
| Special Purposes | Meas. Unit | |
| C1 | Building Site | vg |
| C2 | Demolitions | m2 / vg |
| C3 | Others | m2 / vg |
| D | Construction Operations | Meas. Unit |
| D1 | Protecting | m2 / vg |
| D2 | Clearing, Preparing | m2 / vg |
| D3 | Transporting, Lifting | kg / vg |
| D4 | Forming: Cutting, Shaping, fitting | m2 / vg |
| D5 | Treatment: drilling, boring | m2 / vg |
| D6 | Placing: laying, applying | m2 / vg |
| D7 | Making Good, Reparing | m2 / vg |
| D8 | Cleaning Up | m2 / vg |
| D9 | Other Construction Operations | m2 / vg |