B08.04. Emissions, Revisions and Versions

In a project phase, there will be versions of the project, first emissions of sheets and revisions’ sheets.

Revisions:

The changes reflected in a drawing have a revision number, that is identified in the sheet. The description of the revision is included in the legend of the sheet.        

Versions

When there are several changes / revisions, it might be necessary to issue a new version of the project. This decision is made by the Project Manager. A new copy of the file must be created.

 NOTE: The sheet list can be issued several times, with the new revisions of the sheets, but this does not mean that it is necessarily a new version of the project.